Back Up the Vault
You can back up and restore the vault.
Always copy the complete vault, never make partial backups. When restoring a vault, always restore the complete vault. The vault contains SolidWorks Workgroup PDM configuration data in addition to project documents.
-
Back up the vault regularly.
-
Store the backup copy on a server different from the one where the vault resides.
-
Test the backup to be sure your procedure works correctly.
-
Stop the vault service, or lock the vault on the VaultAdmin Vault Settings tab, so clients cannot check in documents, change ownership, etc.
-
Clear the options on the VaultAdmin Vault Settings tab for validating the vault on startup, especially if the vault is large.
You can replace the current vault copy with a backup copy of the vault, if you want to revert to a previous version of the vault.
To make a backup copy of the vault:
-
Stop the Workgroup PDM vault service.
-
Stop the Windows Indexing service.
-
Save a copy of the current vault, and name it VaultData_mm_dd_yy, where mm_dd_yy is the date. The default name of the current vault is named VaultData.
-
Start the Windows Indexing service.
-
Start the Workgroup PDM vault service.
To replace the current vault copy with a backup copy:
-
Stop the Workgroup PDM vault service.
-
Rename the current vault to VaultData_old.
-
Copy the backup vault to the location of the current vault, and rename it VaultData.
-